Sector
Aeronautics
Service
Lean manufacturing
|
Productivity improvement
Need
- Plant disordered growth that implies crossed flows
- Very big and heavy pieces, difficult to be manipulated
Solution
- VSM to decide an organisation system
- Reorganisation of lay-out to put the flows in order, to eliminate their growth and to allow the work following VSM
- Alternative handling means simplification
Achievements
- Lead time reduction: 60%
- Materials movement cost reduction (by number of movements and meters covered): 37%
- Handling costs reduction (by alternative handling means): 32%
|
|
|
|