Lead-time reduction

Sector
Aeronautics
Products
Lead-time and reliability

Needs

Process not strong enough, with a big variability in the lead time and hours / person per plane:

  • Light control of the subcontracted sets, what obliges to modify the assembly plan
  • Deficient materials supply that implies time losses in searching pieces
  • Difficult process to equilibrate as different parts of the plane are involved, and in many cases they are new developments in a big percentage of the plane

Solution

Starting from a strategic deployment in which the value chain is analysed, the main action lines are established:

  • Guarantee and to control the entry conditions of the subcontracted sets in the FAL (Final Assembly Line)
  • Guarantee the availability of needed materials for the assembly and to standardise its flow and location in the plant
  • Equilibrate the operations dividing the final assembly in phases leak of the same length
  • Eliminate the non controlled operations such as “adjust” from the operations chain

Results

Unresolved work hours at the elements entrance in the FAL:

  • Starting situation: 1.500 hrs / plane
    • Final situation: between 0 and 100 hrs / plane
    • Hours/person per plane: 750 hrs / plane reduction
  • Organise the assembly by phases reducing the interferences between different specialities inside the plane
  • Pieces availability improvement at the assembly’s beginning: from 70 to 85%

HADA - Helicóptero Adaptativo Avion

 

 

 

 

 

 

 